- 5 men can complete a certain amount of work in 7 days and 7 women can complete the same work in 9 days. A project manager hires 5 men and 9 women for "x" days to complete some amount of work. After "x" days, he replaces them by 7 men and 7 women who can complete the remaining work in (135/98) days. What is the value of "x"